Ohio Project
Expansion of 28 Sites + 25 Acres
Wauseon, Ohio
- Existing community acquired in December 2021. 109 occupied sites, P2 entitled sites, 25 acres of adjacent land.
- Phase 1 10 Sites Ready for Homes (Sell out in 2.5 months).
- Phase 2 Expansion (28 sites) constructed in 8 weeks. Launched Summer 2022.
- Phase 3 Entitlement Process Underway for 50 additional home sites.
Overview
- The Wauseon, Ohio project has three phases beginning with infilling 10 existing home sites. While the road and infrastructure existed for the Phase 1 cul du sac, lots needed to be prepared and homes ordered. Phase 1 was complete in 10 weeks, with all homes sold.
- A second phase included new roads, infrastructure and the building out of 28 new home sites. The 8 week development project will be complete in early Summer of 2022. Phase 2 homes have premium wooded lots and will consist of multisection homes, many with drywall and front porches.
- Final phase 3 entitlement is underway with discussions regarding the 25 acres across the road from the existing community and an additional 50 home sites.
- All home orders are aligned with market needs for both families and downsizers. New home buyers are attracted to the property from all over the greater Toledo MSA.
Wauseon, OH / Development Video & Photos: